|
|
|
Type 45 ("D" Class) Destroyer
Daring Class
Part 1
Type Designation: Destroyer, Guided Missile (DDG)

(Source: BAE Systems)





|
(Above) Launch of HMS Daring, on 1 February 2006..
(Source MOD) |


|
(Above) HMS Dauntless, the second type 45 destroyer, under assembly in late June
2006 at BAE Naval Ships Govan yard on the Clyde. Blocks A, B and C have been joined on the slipway.
(Source: Neil MacMahon) |


|
(Above) HMS Dauntless, the second type 45 destroyer, under assembly in late June
and mid July 2006at BAE Naval Ships Govan yard on the Clyde. Blocks A, B and C have been joined on the slipway.
(Source: Barry Watson) |


|
(Above) HMS Daring in dry dock at the BAE Systems yard at Scotstoun, 25 July 2006.
(Source: Neil MacMahon) |

|
(Above) Launch of HMS Dauntless on 23 January 2007.
(Source: BAE Systems) |


|
(Above) HMS Daring begins sea trials, 18 July 2007.
(Source: BAE Systems) |


| (Above) HMS Daring back alongside at
Scotstoun, HMS Dauntless can also be seen under construction. 4 August 2008. (Source: David Reid) |
| Ship |
Pennant Number |
First Steel Cut [1] |
Launched |
Delivery &
Commiss-ioned |
In Service [2] |
|
Batch 1 |
| Daring |
D32 |
28 March 2003 |
1 February 2006 |
[July 2009] |
[2010] |
| Dauntless |
D33 |
26 August 2004 |
23 January 2007 |
|
[2010] |
| Diamond |
D34 |
25 February 2005 |
27 November 2007 |
|
[2011] |
|
Batch 2 |
| Dragon |
D35 |
19 December 2005 |
17 November 2008 |
|
[2011] |
| Defender |
D36 |
31 July 2006 |
|
|
[2012] |
| Duncan |
D37 |
26 January 2007 |
|
|
[2013] |
Notes:
1. Because of the modular nature of the Type 45
construction, the traditional milestone of the keel being "Laid Down"
has been replaced by a ceremonial "cutting
the first sheet of steel". VT
Shipbuilding and BAE Systems Naval Ships (now both part of BVT Surface
Fleet) have announced very different dates for the cutting of steel, the
table follows VT announcements but as result is different from latter
BAE announcements.
2. In January 2004, BAE Systems announced that it would not be able
deliver the first Type 45 until 2008 and a revised ISD of May 2009 was
subsequently agreed with the MOD, this has since slipped by another
seven months. In late 2004, the MOD pushed
back its desired ISD's of units T45-03 to -08 by one to four years
compared with the prior plans but the dates finally with
contractors in August 2007 showed less of a slip for later units, which
were already under construction by that stage.
Specification
Note that some characteristics and specifications may still change in
later ships. It's also been reported that several systems (as
indicated) may not be initially fitted.
Displacement: 5,800 tonnes light; 7,350 tonnes deep load; 8000
tonnes design max
Dimensions: length 152.4 m overall, 143.5m lbp; beam 21.2 m;
draught 5.7 m (500.0 x 69.6 x 18.7 feet). Air draught 39m; depth
(1 deck) 12.6 m
Speed: 29 knots max dash (over 31 knots on trials); 27 knots max sustained; cruise 18 knots
Endurance: 7000nm at 18 knots
Engines: Integrated Electric Propulsion (IEP); 2 x WR21 Rolls
Royce-Northrop Grumman ICR gas turbines generator sets (WR-21 turbines
down-rated to 21.5 MW each, Alstom supplied alternators at 21MW); 2
Alstom 15-phase electric induction motors (rated at 20MW each at 150
rpm); max total output 40MW (53,648 shp); 2 shafts; 2 x Wartsila
12V200 diesel Hitzinger alternator sets (rated at 2.2MW each) for
low speed propulsion and ship service requirements.
Complement: 190 crew (20 officers, 170 ratings), berthing for 235
including up to 60 Royal Marines.
Missiles:
SAM: PAAMS - Typical mix of: 32 Aster 30; active doppler radar
seeker; 3 km to 80 km (1.6 to 45 n miles) at 4.0 Mach; warhead 15 kg
(84C); and 16 Aster 15; active doppler radar seeker; 1.7 km to 15 km (1
to 8 n miles) at 15,000 m (49,000 feet) altitude at 4.0 Mach; warhead
? kg (84C); 6 x 8 cell DCN Sylver A50 Vertical Launch System
SSM: Fitted for but not with 8 ( 2 x 4 launchers) McDonnell
Douglas Harpoon; active radar homing; up to 130 km (70 n miles)
Guns: 1 Vickers 4.5 in (114 mm)/55 Mk 8 Mod 1; 25 rds/min to
27 km (15 n miles) anti-surface; 6 km (3.3 n miles) anti-aircraft; 800
rounds; weight of shell 21 kg.
2 Raytheon 20mm Phalanx Block 1B Mk15 CIWS;
2 DES/MSI DS 30B 30 mm/75; REMSIG variant, 650 rds/min to 10 km (5.4 n
miles) anti-surface; 3 km (1.6 n miles) anti-aircraft; weight of shell
0.36 kg
Torpedoes: None [Provision for fitting 4 Cray Marine 324 mm fixed
(2 twin) tubes. Marconi Stingray; active/passive homing to 11 km (5.9 n
miles) at 45 kt; warhead 35 kg (shaped charge); depth to 750 m
(2,460 ft). Automatic reload in 9 minutes.]
Countermeasures: Thales integrated intercept and jammer suite
Decoys: 4 8-tube decoy RL; 4 DLJ(2) floating decoy launchers (offboard
decoy rounds - Mk251 IR Active Decoy Round (ADR), Mk214 Seduction Chaff,
Mk216 Distraction Chaff.
Type 2070; J-SSTD (SLQ-25A(V)) active and passive towed torpedo decoy.
Combat data systems: BAE Insyte CMS-1; Links 11, 14 and JTIDS 16;
Lockheed Martin CEC [uncertain, was until May 2005 planned for fit from
2012].
Astrium SCOT 3 SATCOM.
Weapons control: GWS 60 (for SSM). GWS ? (for SAM).
Radars: Long Range Air/Surface Search & IFF: Alenia Marconi
Systems S1850M Smartello; D-band
Surveillance & PAAMS Fire Control: BAE Systems Sampson MFR; E/F
band
Navigation: Raytheon Pathfinder Mk2
IFF: 1010/1011.
Sonar: Ultra-EDO Type 2100 medium-frequency system; bow-mounted;
active search and attack.
Helicopter: 1 Westland Lynx HMA.8 or AgustaWestland Future Lynx
(flight deck and hanger sized for Merlin HM.1)
Notes:
Project designation: Type 45 URD Issue 3
Status: Main Gate approval, contract awarded to Prime Contractor
in November 2000
In Service Date: December 2009
The Type 45 Daring Class destroyers will provide a much needed
replacement for the Type 42 air defence destroyers. It was
originally planned that there would be 12 ships, and all would be
in-service by 2014. However in July 2004 the planned buy was
reduced to 8, with the expectation that they would all to be in service
by 2017.
Official approval for the first three units was announced on 11 July
2000 and the order for three complete ships (Batch 1) was placed on 21 December with the Prime Contractor
(BAE Systems Electronics). The prime contractor
subcontracted the construction and outfitting to BAE Systems Marine
yards on the Clyde and VT Group's new facility at Portsmouth Naval Base.
On 18 February 2002 the order was
increased from 3 to 6 units - but it later emerged in early 2005 that
the contractual increase was for the hull platform only. The
extra three (Batch 2) hulls were contracted for - but many of their
systems, the final integration and fitting-out weren't - this finally
occurred in August 2007.
In June 2005 the BAE Type 45 PCO submitted revised pricing
for the completion of the Batch 2 units (T45-04 to 06) and - as an option
- provided pricing for the hoped for final two
units (T45-07 and 08). Hopes for an order by the end of 2005
failed to materialise amidst hints that the MOD was looking for a much
lower price.
In late 2005 the MOD started to refer to "up to eight" Type 45
destroyers, and were decreasing chances that T45-07 and 08 would
ever be ordered due to inadequate funding.
In December 2006 BAE bid for
the completion of some or all of the Batch 2 units, and re-tendered for one or two additional units.
On 19 June 2008 the Government finally admitted - as long expected -
that the option for the seventh and eight Type 45's would not be taken
up, and only six Type 45 destroyers would now be built.

Historical Background
The Royal Navy recognised the need for a replacement air defence
capability as long ago as the mid 1980s, and the need to upgrade the
GWS30 Sea Dart system was realised even earlier, during the Falklands
Campaign. Improvements to the Sea Dart missile have been aimed
primarily at countering anti-ship missiles, against which it was not
designed. Progressive improvements in the threat, notably in
stealth, speed, resistance to countermeasures and sophisticated terminal
homing, have overtaken the further development potential of the Sea Dart
and by the mid-eighties it was realised that a complete replacement
system was clearly needed.
A national programme to replace the Type 42 Destroyers was the
originally preferred procurement route and UK-only Type 43 and 44
programmes were considered. However these were quickly discarded
when it was realised that a number of European navies had similar
requirements in the same timescale. From this realisation grew the
NATO Replacement Frigate (NFR 90) project which at its height
encompassed 7 nations. However, the inability to reconcile
national variations of the base design and the bureaucratic complexity
of project management led to the UK leaving the consortium, which
shortly afterwards collapsed completely. The demise of NFR 90
spawned two separate projects: the first, involving the Netherlands,
Germany and subsequently Spain has lead to the F100/F124/LCF classes of
ships based around the US Aegis AAW system deploying the Standard
missile; the second started as an agreement between France and UK,
joined soon afterwards by Italy, to build a Common New Generation
Frigate comprising the Principal Anti-Air Missile System (PAAMS)
deploying the Aster missile in the "Project Horizon"
ship. Unlike F100/F124/LCF, which is based on loose collaboration
encompassing numerous national variations, CNGF had a tight Tri-partite
Staff Requirement in which national variations were resisted, ultimately
leading to its demise in 1999 when it proved impossible - despite many
years of effort - to agree a viable and equitable industrial structure
for the project. The UK also objected to work-shares for France
and Italy that were completely disproportionate to their expected orders
(in 1998 they were willing commit to just 2 ships each, compared with
UK's 12), and the unjustifiable French domination of the project's
management. In early 1999 the UK reluctantly withdrew from the
Horizon programme (but not from the PAAMS project) and announced that it
would instead develop a national design - the Type 45 destroyer.
Italy and France are continuing to develop a slightly smaller and
substantially cheaper version of Horizon, still armed with
PAAMS, of which they each ordered two ships in October 2001.
Role & Capabilities
With an anticipated service life of 25 years, the new destroyers will
form the back-bone of the RN's anti-air warfare (AAW) capability until
at least 2035. Although potentially extremely powerful ships, to
save money several major systems (anti-ship missiles, torpedo launch
systems) which were originally planned to be fitted will not now, and
other systems have been considerably down-graded (an existing 4.5" gun
will be fitted rather than a planned new 155mm gun, old Phalanx CIWS
mounts fitted rather than a new Inner Layer Missile System, a Lynx
helicopter carried rather than the new Merlin, and plans for an
anti-ship missile dropped). It's hoped that these deficiencies
will be remedied during the life of the class. A senior Royal Navy
source once said that the ships "are not the best that we could build, but we
are getting a dozen, and the armament enhancements to the later ships
will improve their capabilities considerably." Sadly a dozen
is now very unlikely.
Key user requirements (KUR's) are:
| KUR1 |
PAAMS |
The T45 shall be able to protect with a Probability
of Escaping Hit of ??, all units operating within a radius of 6.5km,
against up to 8 supersonic sea skimming missiles arriving randomly
within ?? seconds. |
| KUR2 |
Force Anti-Air Warfare Situational
Awareness |
The T45 shall be able to assess the Air Warfare
Tactical Situation of 1000 air real world objects against a total
arrival and/or departure rate of 500 air real world objects per
hour. |
| KUR3 |
Aircraft Control |
The T45 shall be able to provide close tactical
control to at least 4 fixed wing aircraft, or 4 groups of aircraft
in single speaking units, assigned to the force. |
| KUR4 |
Aircraft Operation |
The T45 shall be able to operate both one organic
Merlin (Anti-Submarine Warfare and Utility variants) and one organic
Lynx Mk8 helicopter, although not simultaneously. |
| KUR5 |
Embarked Military Force |
The T45 shall be able to operate an Embarked
Military Force of at least 30 deployable troops. |
| KUR6 |
Naval Diplomacy |
The T45 shall be able to coerce potential
adversaries into compliance with the wishes of Her Majesty’s
Government or the wider international community through the presence
of a Medium Calibre Gun System of at least 114mm. |
| KUR7 |
Range |
The T45 shall be able to transit at least 3000
nautical miles to its assigned mission, operate for 3 days and
return to point of origin, unsupported throughout, within 20 days. |
| KUR8 |
Growth Potential |
The T45 capability shall be able to be upgraded to
incorporate new capabilities or to enhance extant capabilities
through displacement margins of at least 11.5 %. |
| KUR9 |
Availability |
The T45 shall have a 70% availability to contribute
to Maritime Operations over a period of at least 25 years, of which
at least 35% will be spent at sea. |
As of November 2006, KUR 4 will not be met and KURSs 2 and 3 may not
be met when HMS Daring enters service in late 2009.
|